[google-translator]

DISASTER RECOVERY

When ICS arrived onsite, this was what the typhoon damage looked like. ICS was tasked with surveying and documenting the damage before emergency sourcing materials to rebuild the towers and have them fully operational again.

image[9]

Without power on the island, conditions were rough for the locals and ICS team as well.

ICS Job Complete

This is how we left the towers, rebuilt, upgraded and the power plant ready to produce power.

Cooling Tower Disaster Recovery

When the Leyte typhoon destroyed Malitbog and the cooling towers, Energy Development Corp (EDC) needed help fast. ICS was first on the ground in the Philippines to provide emergency assistance by surveying damage and jumping into action to emergency source materials and supply all services for the rehabilitation for three power plants with multiple towers.